Calculate critical path float

Calculate total float from earliest and latest start times.

Paper 1, Paper 2 5 marks Difficulty 4

Calculate critical path float - exam scenario

Confirm the modelling meaning first. In a regional bank project network, an activity has earliest start 4 and latest start 7. Calculate its total float. Enter the requested value and choose the interpretation that matches the result.